Works Update 19/08/19

We will be closing Laurie Avenue at the junction with Ashburton road on Thursday 5th September 2019 between 09:30 and 15:30. Access to properties in Laurie Avenue will be available at all times, but via Rosemary Avenue only.

We will be closing Elmwood Avenue at the junction with Ashburton road on Friday 6th September 2019 between 09:30 and 15:30. Access shall be available via Applegarth Avenue and Applegarth Close at all times.

The purpose is to construct speed tables in both locations.

Works Update 05/08/19

Week commencing 12th August we are doing the drain lining to be followed by final surfacing on the footpath / cycleway w/c 19th August for approximately 2 weeks.

There is 1.2km of 4m wide footpaths to resurface. What is there currently is only a temporary surface. The covers on the footpaths have been raised in readiness for the footway surfacing. We have put temporary tarmac ramps in place around these to prevent it being a trip hazard.

The surfacing work on the footpaths will be completed in 300m stretches with temporary traffic lights operating to create a safety lane for our workforce and machinery alongside the footpath.

There shall be footpath diversions signposted during this work.

About the Scheme

Griffiths are delivering the next phase of ongoing development to the West of Newton Abbot on behalf of Devon County Council. Work along Ashburton Road will improve facilities for pedestrians and cyclists that will link new housing to the west, with educational sites and the town centre to the east.

Please note this scheme is not currently registered with the Considerate Constructors Scheme but will abide by the Code of Considerate Practice.