Progress and Timeline

October 2021: Project Started
October/November 2021: Enhanced junction of Marketfield and Fore Street
November 2021: Started work on new islands, drainage, kerb lines and gulley’s – Marketfield and Boden
November 2021: Stringfellow sculpture removed and reduced the height of path to the same level of the road
December 2021: Paving commenced North side of Fore Street / Tree pits created rear of Sainsbury’s
December 2021 onwards: Paving Holyrood /Fore Street Replaced and upgraded water channels
January/February 2022: Installation of granite kerbs in Holyrood/Fore Street
February 2022: Kerb, new footpath and tarmac Boden Street – Island complete