Traffic Updates

23rd October 2020 – Traffic Management Update

On Monday 2nd November we will be installing 3-way Temporary Traffic Lights at the junction of Hullavington Road and the A429, as we enter our busiest phase of work. We anticipate they will be in place for 4 weeks whilst we continue building the new roundabout and carriageway to replace this junction. There is also drainage work to complete in this section as well as ducting for services.

Our TM Drawing can be seen here .

The pink and red area is the roundabout under construction and safe working area which reduces road capacity for traffic until complete. We appreciate your patience and co-operation during this time.

9th October 2020 – Traffic Management Update

There has been a one week delay in the installation of the temporary traffic lights on the Hullavington Road as below. These will now be installed on Wednesday 14th October. The reason, duration and plan remains the same.

October 2020

We shall be setting up a set of 2-way temporary traffic lights on the Hullavington Road where our new road links onto the existing one.

Click here to view our TM plan.

These will be in place on Wednesday 7th October for approximately 3 weeks.

At this location we are carrying out the remaining earthworks to formation alongside the existing carriageway. We will then install 2 no. 225mm drainage pipes where the existing ditch runs, as this will then run underneath the new link road. At either end of these drainage pipes where they join back into the ditch there will be brick-built headwalls. The carriageway construction of capping stone and subbase will be installed and compacted.

The timings of the temporary lights will be set up in such a way as to minimise any disruption to traffic flows and will be regularly monitored to assess if any amendments are required.