Progress and Timeline
- June 2021 – Sept 2021 – Site set up/Site clearance/hedge translocation.
- Sept 2021 – Jan 2022 – Cut & fill / Road box excavation/ Drainage work
- Feb 2022 – April 2022 – Kerbs & Beany blocks installation/ Services diversions/ Base & Binder course to Perry Cross from A382
- April 2022 – June 2022 – Culvert work/ Street Lightings & signs/ Base Binder Course to Houghton lane from Perry cross.
- Footpaths/ Wearing Course to the whole new Link Road
- Top soiling & Landscaping