Progress and Timeline

  • June 2021 – Sept 2021 – Site set up/Site clearance/hedge translocation.
  • Sept 2021 – Jan 2022 – Cut & fill / Road box excavation/ Drainage work
  • Feb 2022 – April 2022 – Kerbs & Beany blocks installation/ Services diversions/ Base & Binder course to Perry Cross from A382
  • April 2022 – June 2022 – Culvert work/ Street Lightings & signs/  Base Binder Course to Houghton lane from Perry cross.
  • Footpaths/ Wearing Course to the whole new Link Road
  • Top soiling & Landscaping