Construction Phasing Plans

The phasing plans below identify the phases of work that will be undertaken to complete the works between Aztec West Roundabout and the Aldi Roundabout.

These plans identify the traffic management restrictions and the areas where work will be taking place. The progress of these works will be regularly updated via our Community Website and the Bradley Stoke Journal.

 

Aztec West to Aldi Roundabout – Phase 2.1

Historical

bsw-zone-1

Aztec West to Aldi Roundabout – Phases 2.1 & 3.
Start Date: April 2016
Approximate Duration: 3 months
Left turn into Woodlands Lane (only) open. No right turn into or out of Orchard Gate. Footpath diversions installed when required. Patchway Brook zebra crossing open. Orchard Gate crossings closed. Road widening works continuing to Woodlands Lane to Orchard Gate (North) and Orchard Gate to Patchway Brook (North). Bristol Water diversion works commenced to Woodlands Lane (South) and A38.

bsw-zone-2

 

Aztec West to Aldi Roundabout – Phase 3.1A
Start Date: May 2016
Approximate Duration: 2 months
Left turn into Woodlands Lane (only) open. No right turn into or out of Orchard Gate. Patchway Brook zebra crossing open. Orchard Gate crossings closed. Footpath diversions installed when required. Temporary access/egress works to Orchard Gate to completion. Verge works continuing from Woodlands Lane to Patchway Brook (North). Bristol Water diversion works ongoing to Woodlands Lane (South) and A38.

bsw-zone-3

 

Aztec West to Aldi Roundabout – Phase 3.1B
Start date: June 2016
Approximate Duration: 1 month
Left turn into Woodlands Lane (only) open. No right turn into or out of Orchard Gate. Patchway Brook zebra crossing open. Orchard Gate crossings closed. Footpath diversions installed when required. Orchard Gate road reconstruction works to completion. Verge works continuing from Woodlands Lane to Patchway Brook (North). Bristol Water diversion works ongoing to Woodlands Lane (South) and A38.

bsw-zone-4

 

Aztec West to Aldi Roundabout – Phase 4.1
Start date: June 2016
Approximate Duration: 2 months
Left turn into Woodlands Lane (only) open. No right turn into or out of Orchard Gate. Patchway Brook zebra crossing open. Orchard Gate crossings closed. Footpath diversions installed when required. Orchard Gate road reconstruction works to completion. Verge works continuing from Woodlands Lane to Patchway Brook (North). Bristol Water diversion works ongoing to Woodlands Lane (South) and A38.

bsw-zone-5

 

Aztec West to Aldi Roundabout – Phase 5.1
Start date: August 2016
Approximate Duration: 4 months
Left turn into and out of Woodlands Lane open. No right turn into or out of Orchard Gate. Patchway Brook zebra crossing open. Orchard Gate crossings closed. Footpath diversions installed when required. Orchard Gate and Woodlands Lane splitter and carriageway reconstruction works. Bristol Water diversion works ongoing to Woodlands Lane (South) and A38. Orchard Gate to A38 (South) road widening commenced.

bsw-zone-6

 

Aztec West to Aldi Roundabout – Phase 6.1
Start date: November 2016
Approximate Duration: 1 month
Off Peak (generally nights) surfacing, road markings, and traffic signal commissioning (loop cutting) works. Upon completion, Woodlands Lane and Orchard Gate to be fully openbsw-zone-7