Traffic Information

By clicking on the links you can view the Traffic Management Plans.

  • Construction commences on 4th September 2017 with a Lane 1 (slow lane) closure westbound on the approach to the new junction until Christmas – Plan 1
  • Following Christmas, Lane 2 (overtaking lane) will be closed in both directions to install cross-overs. – Plan 2
  • Between mid-January and end of February the A361 will travel in contraflow to enable resurfacing works to take place during the day – Plan 3, Plan 4, Plan 5, Plan 6