The first road closure on the A350 will be from 20:00 on 25th September 2017 until 06:00 on the 26th September 2017 on both Section 1 between Brook and Badger roundabouts and Section 2 between Chequers and Cepan Park roundabout to form narrow lanes & install varioguard (steel barrier) to prepare for future work. Diversion signs will be posted in advance and the diversion map can be viewed by clicking HERE

 

Traffic Management needs to be in place throughout the length of the works sections on the A350 for the duration of the works.

Drawings from our Traffic Management contractor explaining how this will be implemented are below.  Click on the links below to view.  There will be a temporary speed limit through the traffic management of 40mph.

40mph Temporary Speed Restriction

A350 Traffic Management Phase 3 Section 1 – Brook Roundabout – Badgers

A350 Traffic Management Phase 3 Sections 2 to 6 around Chequers and Cepen Park South Roundabouts